Heavy Industrial Area, Tema - Ghana

Supply and Installation 120tons/hr (NET) Boiler

Project Goal: Increase steam generation capacity for plant operations and ensure operation reliability.

Project Status:
  • Boiler and some of its accessories have been installed.
  • Overall achievement is 80% of project work done.
  • Challenges: Require funds to pay for supply and installation of the fuel oil tanks and the air-cooled condenser and the others before the completion and commissioning of the boiler.