Project Goal: Increase steam generation capacity for plant operations and ensure operation reliability.
Project Status:
Boiler and some of its accessories have been installed.
Overall achievement is 80% of project work done.
Challenges: Require funds to pay for supply and installation of the fuel oil tanks and the air-cooled condenser and the others before the completion and commissioning of the boiler.